Case Study – Chevron, Barrow Island

Client Description  Chevron is one of the world’s largest oil companies and is active in more than 180 countries
Project Type  Lean Six Sigma in Construction
Project Location  Western Australia, Australia
Client size  61,500 Employees
Project Duration  6 months
Client Industry Sector  Oil & Gas

Challenge Faced:

Accelerate construction lead times for building USD 54 billion LNG plant on Barrow Island.

Project Outcome:

• Avoided USD $7.5 million construction costs of new offices.
• Reduced duration of construction contractors on site allowing earlier demobilization.

Project Deliverables:

• Analyzed office space capacity and scheduled availability, and matched with future headcount needs.
• Mapped the size of each team to the size of available offices, and sequenced with availability.
• Relocated 350+ Operations personnel to already-existing construction-phase office facilities, which also reduced travelling distance, waiting time for permits, and increased productivity.
• Gained acceptance from workforce for relocation