Challenge Faced:

Improve supplier on-time delivery performance: A manufacturing supplier of spools (piping)was an estimated 10 months behind schedule. As the spool manufacturer was on the critical path for the LNG construction project, the delayed spools were a critical risk to first-gas target date.

Project Outcome:

• With a 91% increase in outputs the spool manufacturer is no longer on the critical path for the LNG construction project and removed from the riskregister.
• Hard dollar savings in reduced labour and expediting USD$3,200,000.

Project Deliverables:

• Worked with vendor to have vendor improve their own performance (working through influence).
• Value Stream Mapping of entire manufacturing process to identify bottlenecks.
• Focused improved efforts on two key bottleneck processes.
• Conducted a Measurement System Analysis to identify inconsistencies in decision making at pass/fail inspection process. Standardized inspection to reduce rework from 80% to 20%.
• Established a daily Milk-Run to remove waiting time and achieve consistent deliveries of finished spools to client site
• Embedded SOPs for cosmetic inspection to ensure right-first-time inspection decisions